25 person can finish a work in 16 days how many persons are required to finish the work in 10 days
Answers
Answered by
0
16 members
hope so its right
MithuDas:
hi
Answered by
2
here
is your answer
25 person finish a work in 16 day
let x person finish same work in 10 days
16/25=10/x
16×x=10×25
16x=250
x=15.625
therefore it is 16 member
is your answer
25 person finish a work in 16 day
let x person finish same work in 10 days
16/25=10/x
16×x=10×25
16x=250
x=15.625
therefore it is 16 member