25 persons can complete a piece of work in 60 days. They started the work . 10 persons left the work after x days. If the whole work was completed in 80 days , then what is the value of x ?

Answers

Answered by navyatha91
0

Answer:

20 days

Step-by-step explanation:

given,

25 persons can complete a piece of work in 60 days

i.e. 25:60

10 persons left the work

i.e. 25 persons - 10 persons

= 15 persons

the no. of days the 10 persons worked is x days

the work completes by 15 persons in 80 days

i.e. 15: 80

x days = number of days work done by 15 person - number of days work done by 25 person

= 80 days - 60 days

= 20 days

therefore, the 10 persons left the work after 20 days