Math, asked by rajaramjadiya26, 9 months ago

25 workers can complete a task in 150
days. How many workers will be
required to complete the task in 125
days?train train ​

Answers

Answered by rahulvnkt100
4

total work / 25 * work done by each worker = total days .

x/25Y = 150

X = 3750Y

If same amount of work is done by x no. of workers in 125 days , no. of workers is 3750 / 125.

answer is 30 workers

Answered by sagarkpaul
0

Answer:

21 workers

Step-by-step explanation:

No. of workers required to complete the work in 150 days = 25

No. of workers required to complete the work in 125 days = X

.'. 150/25 = 125/X

X = (125*25)/150

= 20.83

= 21 workers