25 workers can complete A work in 18 days working 6 hours per day . In how many days can 20 workers complete the same work working 5 hours per day
Answers
Answered by
4
answer:27 days
days taken by man hour=25×6×18=2700
days taken by 20 men=20×5=100
2700÷1000=27 days