Math, asked by triggerAVS6509, 11 months ago

25 workers can complete A work in 18 days working 6 hours per day . In how many days can 20 workers complete the same work working 5 hours per day

Answers

Answered by pokemonmasters
4

answer:27 days

days taken by man hour=25×6×18=2700

days taken by 20 men=20×5=100

2700÷1000=27 days