25 workers were employed to complete a compound wall in 12 days 5 workers left after working for 4 days the remaining 20 workers complete the work in how many days total job was completed
Answers
Answered by
5
Answer:
14 Days
Step-by-step explanation:
Total work = 25 workers * 12 days = 300
Work done by all the workers in 4 days
= 25 * 4 = 100
Remaining work = 300 - 100 = 200
Remaining Work done by 20 workers in
= 200/20 = 10
Total time taken = 10 Days + 4 Days
= 14 Days