25 workers were employed to complete a compound wall in 12 days 5 workers left after working for 4 days the remaining 20 workers complete the work in how many days total job was completed

Answers

Answered by Adarshk367
5

Answer:

14 Days

Step-by-step explanation:

Total work = 25 workers * 12 days = 300

Work done by all the workers in 4 days

= 25 * 4 = 100

Remaining work = 300 - 100 = 200

Remaining Work done by 20 workers in

= 200/20 = 10

Total time taken = 10 Days + 4 Days

= 14 Days