26 men can complete a piece of work in 17 days. How many more men must be hired to complete the work in 13 days ?
Answers
Answered by
4
this is correct answer
Attachments:
Answered by
3
There are 8 more men needed to complete in 13 days.
Step-by-step explanation:
Since we have given that
Number of men = 26
Number of days = 17
If the number of days = 13.
We need to find the number of more men must be hired to complete it in 13 days.
According to question, it becomes,
Number of more men would be
34-26=8
Hence, there are 8 more men needed to complete in 13 days.