Math, asked by sneharotkar, 8 days ago

27-28 : Total cost of contract to date - 3,83,000
Cost of contract not yet to certified - 23,000)
Value of work certified - 4,20,000
Cash received to date - 3,78,000 () 3,16,1
27. Value of work-in-progress is
(a) * 65,000
(b) * 41,000
(c) 23,000
(d) * 14,000​

Answers

Answered by AmanRatan
0

Answer:

41000 hai anwer hai right

Step-by-stepexplanation: