Math, asked by dhaliwal200105, 6 months ago

27 girls complete an embroidery work in 10 days. H
ow many days will 18 girls take to complete the same work?​

Answers

Answered by shriyathite15782
6

Step-by-step explanation:

27 girls can compete a work in 10 days than,

18 girls can do a work in?

Now do cross multiplication,

27×x=18×10

27x=180

x=180÷27

=6 days

Answered by singhsahil2310
1

Answer:

6 days

Step-by-step explanation:

so pl massage me follow mepl

Similar questions