27 people can repair a building in 15 days, working 4 hours a day. In how many days will 20 people, working 9 hours a day, complete the work?

Answers

Answered by asg3641
1
The answer is 9 days
Answered by HanitaHImesh
0

9 Days are required by 20 people, working 9 hours a day, to complete the work.

Given,

27 People repair a building in 15 days

Hours worked per day = 4 hours

To Find,

Days took by 20 people working 9 hours per day to finish the same work

Solution,

Let the number of days taken be 'x'

Case 1 → 15 days are taken working 4 hours every day by 27 people.

Case 2 → x days are taken working 9 hours every day by 20 people.

Total Working hours required to finish the work  -

Case 1 → 15 * 4 * 27 = 1620 hours

Case 2 → x * 9 * 20 = 180x hours

Since the hours required to complete the work would remain the same for both the situations -

180 * x = 1620

x = 9 days

Therefore, the required number of days is 9.