28. A constructor wants some men and boys to build the temple as it has to be completed in one month
men and 7 boys can do a piece of work in 4 days. It is done by 4 men and 4 boys in 3 days. How long
would it take for one man or one boy to do it?

Answers

Answered by goravjhabakhgmailcom
0

Step-by-step explanation:

W=P*t

Work can be completed by a man in 28days

(28/4)-3=work by 4 men

work can be done by in 16 days day