28 children can do a piece of work in 50 days.how many children are needed to complete the work in 30 days??

Answers

Answered by rathibhagwati3
0

Answer:


Step-by-step explanation:

Let, no. of children be x and required days be y.

This is the case of inverse proportion as the days will decrease the no. of

children would increase.


x 28 a

y 50 30


a = 28*50/30

= 1400/30

= 47 approx


Thus, required no. of children are 47.