29. 2 women and 10 children together take 8 days to complete a piece of work. Ho
many days will 10 children alone take to complete the piece of work if 8 wome
alone can complete the piece of work in 6 days ?
3) 10
4) 24
5) Other than those given as options
. 6 women alone can complete a piece of work in
1) 15
2) 12
Answers
Answered by
2
⇒8 women can do a work in 6 days.
∴ 2 women can do 1/24 work in 1 day.
∴ (2 women + 10 children) can do a work in 8 days.
Hence 10 children can do same work in 12 days.