Math, asked by minakhimahapatra88, 1 month ago

29. If 6 boys can complete a work in 20 days, how many days will be required by 8 boys to finish the same work? ​

Answers

Answered by gaargipatil
0

Answer:

15 days

Step-by-step explanation:

6×20=120

8×x=120

x=120/8=15

solved by inverse proportion method

100% correct ans

pls mark as brainliest ans i need it pls

Answered by nirosha23
0
Clearly this is an inverse proportion because, if the number of boys increases then the days will decrease.
let’s say that it will take x days for 8 men to finish the work.
Therefore- 6*20 = 8x
120 = 8x
x = 120/8
x = 15
Hence, it will take 15 days