29. If 6 boys can complete a work in 20 days, how many days will be required by 8 boys to finish the same work?
Answers
Answered by
0
Answer:
15 days
Step-by-step explanation:
6×20=120
8×x=120
x=120/8=15
solved by inverse proportion method
100% correct ans
pls mark as brainliest ans i need it pls
Answered by
0
Clearly this is an inverse proportion because, if the number of boys increases then the days will decrease.
let’s say that it will take x days for 8 men to finish the work.
Therefore- 6*20 = 8x
120 = 8x
x = 120/8
x = 15
Hence, it will take 15 days
let’s say that it will take x days for 8 men to finish the work.
Therefore- 6*20 = 8x
120 = 8x
x = 120/8
x = 15
Hence, it will take 15 days