2men and 7 boys can do a piece of work
in 4 days. It is done by 4 men and 4 boys
in 3 ays. How long would it take for one
man or one boy to do it
.
Answers
Answered by
1
Answer:
it takes 60 days to do work
(2M+7B)4=(4M+4B)3
M=4B
So
(2×4+7)×4=60 DAYS