Let the man can finish the work in x days and the boy can finish the same work in y days.
Work done by one man in one day = 1/x and work done by one boy in one day = 1/y
On Multiplying eqn. (iii) by 2 and subtract eqn. (iv) from it
Hence, one man can finish it in 5 days and boy in 60 days.