3. 540 men can construct a building in 7 months. How many men should be
iron 5 shirts in
are required to construct a 306 km long road?
removed from work to finish the building in 9 months?
Answers
Answered by
1
hi
You can put this solution on YOUR website!
540*7=3780 worker months
540-420=120 to be removed
420*9=3780