Math, asked by shivjisahu245, 7 months ago

3.
A and B can do a piece of work in 12 days and 8 days respectively. A started at it for 2 days and
then was joined by B. Find the total time taken to complete the work

Answers

Answered by prativasahoo198021
1

Answer:

bro this question had done by me tomorrow

Step-by-step explanation:

answer is 1day 15 hour , of my answer is wrong then dont like it

Answered by akaswan
7

Answer:

follow kardo kab SA ek thanks hi da rahe ho