3. A and B together can do a piece of work in 12 days while B alone can finish it in 30 days . in how many days can A alone finish the work?
Answers
Answered by
0
Step-by-step explanation:
B's 1 day work =1/30
A and B's 1 day work is 1/12
so
1/A+1/B=1/12
1/A+1/12=1/12
1/A=1/12-1/30
1/A=30-12/30×12
1/A=18/360
1/A=1/20
A=20
Answered by
0
Answer:
20 days
Step-by-step explanation:
A can do a work in n days. Then A's one days work will be 1/n
Since A and B can do a job in 12 days,
∴1/A+1/B=1/12→1
But B can finish the work in 30 days.
∴ 1/B=1/30 →2
Substituting 2 in 1 we get
⇒1/A+1/30=1/12
Taking 1/30 to the right side.
⇒1/A=1/12-1/30
⇒1/A=5-2/60 Taking LCM
⇒1/A=3/60
⇒1/A=1/20
therefore A alone can complete the work in 20 days.