3. A can do a work in 15 days and B in 20 days.
if they work together on it for 4 days, what
fraction of the work will be left?
Answers
Answered by
2
Answer:
The 3 was remaining 30 is the right answer
Answered by
5
Answer:
Amount of work A can do in 1 day=
1 /15
Amount of work B can do in 1 day =
1/ 20
Amount of work done by A and B in 1 day=
1/ 15 + 1/20 = 7/60
Amount of work A and B can together do in 4 days =4× 7/60 = 7/15
Fraction of work left = 1 - 7/15 = 8/15