3. A can finish the work in 18 days and B can do the same work in 19
the work in 18 days and B can do the same work in 15 days. B alone worked for 10 days
and left the job. If A alone has to finish the remaining work, the number of days it takes is
Answers
Answered by
0
Answer:
I also need this question 's solution
Answered by
1
Answer:
Step-by-step explanation:
18, 15 LCM = 9o
efficiency = 5,6 (A,B)
in first 10 days B did = 6*10 = 60 units
left to be done = 90-60 = 30 unit
This done by A now in = 30/5 = 6 days .(Ans.)