3
Abani and Anwar complete a work separately in 20 and 25 days respectively.
After 10 days of their working together, they both left then Sukhen came and
completed the remaining work in 3 days. If Sukhen alone would do the work,
let's calculate how many days he would take to complete the work.
Answers
Answered by
1
Answer:
30 days
Step-by-step explanation:
step by step explanation is given in the pic attached
Attachments:
Similar questions