3) Ajay takes 6 days more than those of Vijay to complete certain work. If they
work together they finish it in 4 days. How many days would it take to
complete the work if they work alone?
Answers
Answered by
1
Step-by-step explanation:
Total day take by mohan and ajay is 4 day if
ajay take 6 day more than vijay
Let vijay take x day to complete work
then , ajay take x+6 day
if they work together they completed work in 4 days
so in one day
1/x +1/6 +1/x = 1/4
x = 24 day take by vijay and ajay take 30 day when they work alone
Hope this answer help you !!!!!