3) An agile team with six developers uses iterations that are each three weeks long. The team estimates it can
complete 12 story points per iteration, and the total project duration is scheduled at 36 weeks. Identify how to
calculate the team's velocity.
Options:
The number of ideal days divided by six
The total work effort measured as story points divided by the number of iterations
The number of weeks in the iteration multiplied by six
The amount of developer time multiplied by the number of weeks in each iteration
for
Answers
Answered by
11
Answer:
ᴀ❣ɴ❣s❣ᴡ❣ᴇ❣ʀ❣
thє fírѕt vєrѕíσn íѕ αctuαl vєlσcítч αnd ínvσlvєѕ dívídíng thє tσtαl numвєr σf ѕtσrч pσíntѕ cσmplєtєd вч thє numвєr σf ѕpríntѕ. fσr єхαmplє, íf thє dєvєlσpmєnt tєαm hαѕ cσmplєtєd α tσtαl σf 70 pσíntѕ σvєr twσ ѕpríntѕ, thє tєαm'ѕ αctuαl vєlσcítч wσuld вє 35 pσíntѕ pєr ѕprínt.
ʜ㋡ᴏ㋡ᴘ㋡ᴇ㋡ ɪ㋡ᴛ㋡ ʜ㋡ᴇ㋡ʟ㋡ᴘ㋡s㋡ ᴜ㋡
Answered by
1
Answer:
the number of ideal days divided by six
Similar questions