Math, asked by HemanthPilla, 5 months ago

3 boys can complete a work in 17 days. 1 boy can complete it in:​

Answers

Answered by hiteshsharma25031981
0

3/17 =1/x

=>x=17/3 days

please mark my answer as BRAINLEST as I need only 5 BRAINLEST answer to reach next rank

please please please help me

follow me

Answered by ramesh888
2

Step-by-step explanation:

3 boy can complete a work in 17 days.

first we can find unit

total work = number of workers ×number of days

=3*17

=51

51unit is one boy

1*b

1*51

=51 days for one boy