3. If 1800 persons can finish the construction of a building in 40 days, how many persons are required to complete the construction of the building in 24 days?
Answers
Answered by
2
ANS :- 3000 Persons
- 1800 persons can complete a work in 40 days
- number of persons for completing the work in 24 days
product of number of persons and number of days remain same .
ie ,
- Let the number of persons be x ,
- 1800 × 40 = x × 24
- x = 1800 × 40 / 24
- x = 3000
Ie , 3000 persons are required for completing the work in 24 days