3. If 36 men can do a piece of work in 25 days, in how many days will 15 men do the
same work?
Answers
Answered by
0
Given -
36 men can do a piece of work in 25 days.
To find -
15 men do the work in how many days
Solution -
Let, 15 men do the work in x days.
As, we have to complete the same work.
36 men can do a piece of work in 25 days.
Total work =
15 men do the work in x days.
Total work
So, equate both the terms
Divide 15 and 25 by 5 we get
Divide 36 by 3 we get
Hence,
15 men do the work in 60 days .
Answered by
0
Step-by-step explanation:
Given that
36 men can do a piece of work in 25 days
To find
day require to work by 15 men
Solution
let x is the days require for 15 men
then
hence 60 days require to do work by 15 mens