3. If 36 men can finish a piece of work in 25 days, how many days will 15
men take to do it?
4. Find:
a) 30% of 700 b) 95% of 95
5. Find Simple interest:
Principal = Rs.4000, Rate per annum = 15%, Time = 2years
6. If 25% of a journey is 750 km, how long is the whole journey?
7. If 30% of a sum of money is Rs 270, what is the total sum of money?
Answers
Answer:
Please mark me as Brainliest.
Step-by-step explanation:
3. Given, 36 men can finish a piece of work in 25 days
=> The number of man-days = 36*25 = 900
Let x be the number of days taken by the 15 men to do the piece of work
=> The number of man-days = 15x
But the number of man-days remains constant.
=> 15x = 900
x = 900/15 = 60
=> 15 men take 60 days to complete the piece of work
.
5. simple interest formula: 4000 × 8 × 5/100 = Rs. 1600
6. 25% of x = 750
x * 25/10 = 750 km
x = 750 x 100/25
x = 3000 km
30% of sum of money is rupees 270
then 1% = 270/30
=9
then 9×100=900 rupees.
Step-by-step explanation:
36 men can finish a piece of work in 25 days.
no. of man-days =36×25=900
let the x be the no. of days taken by the 15 men to do a work.
no. of man-days =15x
no. of man -days remains constant
15x =900
x=900/15=60
then, 15 men take 60 days to complete the piece of work.