Math, asked by yuvrajt, 3 months ago

3.
If a job is to be finished in 36 days instead of 60 days, how many times the original number of
labourers should be employed?
a)3/2
b)5/3
c)3/5
d)15/8​

Answers

Answered by Itzsweetcookie
6

Step-by-step explanation:

ANSWER

Let there be x men originally.

x men finish the work in 60 days and (x+8) finish it in 50 days.

=x men finish the job in 60 days.

=1 man can finish it in 60x days.

=(x+8) men can finish the job in 50 days.

=1 man can finish it in 50(x+8) days.

=Therefore,

=60x=50(x+8)10x=400

=x=40

Hence, there were 40 men originally.

Answered by Anonymous
3

Answer:

40 labourers should be employed