Math, asked by kalyanichaudhry09, 6 months ago

3. If a man can do a work in 32 days, in how
many days will 24 men complete the same
work?​

Answers

Answered by baski3d
1

Answer:

Yes! Here is your answer!

Step-by-step explanation:

One man does 1/32 of the work in one day. 24 men will do 24/32 of the work in one day. It will take 32/24, or 1 1/3 days, for 24 men to get the job done.