3. If six men can do a piece of work in 6 days, then 3 men can do the same work in……….days
Answers
Answered by
2
Answer:
12days
Step-by-step explanation:
6 mens = 6 days
6 half is 3
then 2×6
12 days answer
hope its helpful to you.
Answered by
1
Answer:
Step-by-step explanation:
Work done by 6= work done by 3
6×6 = 3 × x
x=36/3
x=12 days