3. In how many days of working 8 hours each day, can 12 men do the same work as 10 men working 9
hours a day do in 16 days?
Multi
Answers
Answered by
2
Answer:
the work done by 10 men in 16 days working 9 hours per day would be equal to the work done by 12 menin x days working 8 hours per day.12*8*x = 10*16*9You will get the value of x = 15. So they will need 15 days to complete the same amount of work.
Answered by
0
Now, the work done by 10 men in 16 days working 9 hours per day would be equal to the work done by 12 men in x days working 8 hours per day. 12*8*x = 10*16*9You will get the value of x = 15. So they will need 15 days to complete the same amount of work
Similar questions