Math, asked by ravindratripathi8482, 8 months ago


3. In how many days of working 8 hours each day, can 12 men do the same work as 10 men working 9
hours a day do in 16 days?

Answers

Answered by raginikri2007
3

Answer:

Assume that the number of days required be x.

Now, the work done by 10 men in 16 days working 9 hours per day would be equal to the work done by 12 men in x days working 8 hours per day.

12*8*x = 10*16*9You will get the value of x = 15.

So they will need 15 days to complete the same amount of work.

Hope this Helps :)

Similar questions