3. It took 120 days for 4 men to build a wall. How many days would it take one man
to build the same wall?
Answers
Answered by
2
Answer:
30 days
Step-by-step explanation:
if it took 120 days for 4 men
then x days for 1 man
= 120 * / 4
= 30 days
Therefore, 1 man takes 30 days to complete the work
hope it helps
Pls mark it as brainliest
Answered by
0
Answer:480 days
Step-by-step explanation:
= 4 men takes 120 days to built the wall. =1 man take (120*4)days=480 days.Ans. [obiously 1 man take more time.}