3 man or 5 women for 8 boys can finish a work in 38 days then the number of days taken by 6 men and 10 women and 6 boys to finish the work in how many
Answers
Answered by
1
Answer:
To be able to give an answer, let’s assume that men, women and boys do have the same efficiency at work, and that the job is parallelizable.
Then we know that 3+5+8=16 persons make 1 job in 38 days.
So 6+10+6=22 persons will make 22/16 jobs in 38 days.
And consequently 1 job will take 38/(22/16) = 38*16/22 = 27 days 15 hours 16 mins 21 sec to complete.