3 man whitewash a house in 4 days how much men are required if the work has to finished in 3 days

Answers

Answered by Anonymous
6
ANSWER :
_________

Number of men required to whitewash a house in 4 days = 3.

Number of men required to whitewash a house in 1 day = 3 × 4 = 12

Number of men required to whitewash a house in 3 days = 12 / 3 = 4 men

=> 4 men are required.