3 men, 4 women and 6 children can complete a work in 7 days. A woman does double the work a man does and a child does half the work a man does. How many women alone can complete this work in 7 days ?
A) 6 B) 9 C) 5 D) 7
Answers
Answered by
12
Answer:
: D) 7
Explanation:
Let 1 woman's 1 day work = x.
Then, 1 man's 1 day work = x/2 and 1 child's 1 day work x/4.
So, (3x/2 + 4x + + 6x/4) = 1/7
28x/4 = 1/7 => x = 1/49
1 woman alone can complete the work in 49 days.
So, to complete the work in 7 days, number of women required = 49/7 = 7.