Math, asked by raunit865, 9 months ago

3 men, 4 women and 6 children can complete a work in 7 days. A woman does double the work a man does and a child does half the work a man does. How many women alone can complete this work in 7 days ?

A) 6 B) 9 C) 5 D) 7

Answers

Answered by Anonymous
12

Answer:

: D) 7

Explanation:

Let 1 woman's 1 day work = x.

Then, 1 man's 1 day work = x/2 and 1 child's 1 day work x/4.

So, (3x/2 + 4x + + 6x/4) = 1/7

28x/4 = 1/7 => x = 1/49

1 woman alone can complete the work in 49 days.

So, to complete the work in 7 days, number of women required = 49/7 = 7.

Similar questions