3 men 6 women do a work in 16 days then in how maany days 12 men and 8 women will complete the work?

Answers

Answered by Raghuroxx
0

Answer:

ATQ,

3men×16=6women ×16

Total work=3×2×16=96 units

One day work of(12m+8w)

=12×2+8×1=32 units

Total time taken by (12m+8w)

=96/32=3 days

Step-by-step explanation: