3 Men, A, B, and C complete a work in such a way that A works for all the day. B works for 1st and 2nd day and C works for 3rd, 4th and 5th day. If B+C can do as much work in 2 days as A alone does in 3 days. In how many days A, B and C alone do the work If B+C can complete the whole work without the help of A in 6 days ?
Please solve this question by short trick
Answers
Answer:
A can complete the work in 9 days
B can complete the work in 18 days
C can complete the work in 9 days
Step-by-step explanation:
B and C can do as much work in 2 days as A does in 3 days (Given)
∵ B and C finish a work in 6 days (Note: 2 multiplied by 3 = 6)
∴ A alone can finish the work in 9 days ( 3 multiplied by 3)
Let work done by B in one day is and work done by C in one day is
Work done by A in one day =
According to the question
or,
or, ........ (i)
Again, since B and C can complete the work in 6 days
∴
or, ............(ii)
Multiplying eq (ii) by 2 and subtracting it from eq (i)
or,
Putting the value of y in eq (ii)
or,
or,
Thus, in 1 day B completes work
Therefore, B can complete the work in 18 days
Similarly, C can complete the work in 9 days (∵ in 1 day C does work)
Hence,
A can complete the work in 9 days
B can complete the work in 18 days
C can complete the work in 9 days
Answer:
3 3/5
Step-by-step explanation:
Step 1:
1. AB
2.AB
3.AC
4.AC
5.AC.
Step 2 : Time Efficiency
A 3 2
_______ = __ = __
B + C 2 3
Step 3:
Given,
B and c can together complete the work in 6days without the help of A
So,
Total work = 6 * 3 = 18
From step 1
We get
5A +2(B+C)+ C = 18
10+ 6 +C = 18
C=2
A:B:C
2:1:2
So, 18/5 = 3 3/5