Math, asked by anuhansdak1, 9 months ago

3 men and 2 boys finished a work in 6 days . 5 men and 7. boys finished the same work in 3 days . how many days 2 men and 5 boys can complete this work​

Answers

Answered by rohitrs0908
5

Answer:

Step-by-step explanation:

3 men + 2 boys complete work in 6 days.

=> 6 men + 4 boys can complete in 3 days.

We further know 5 men + 7 boys can complete work in 3 days.

=> 1 man = 3 boys

=> 11 boys can complete work in 6 days.

Now 2 men and 5 boys means 11 boys.

=> They complete work in 6 days.