3 men can complete a piece of work in 6 days. Two days after they started the
work, 3 more men joined them. How many days will they take to complete the
remaining work?

Answers

Answered by royalh955
0

Answer:

1 day

Step-by-step explanation:

PLEASE MARK ME AS BRAINLIEST

Answered by nikhiladitya18
1

Answer:ANSWER =2

Step-by-step explanation:

(3 men) (6 days) = ( 3 men x2 days) + (3+3) x men+D days

18 - 6 = 6 x D

12/6  = D

answer  D = 2