Math, asked by geetikasuri77, 19 days ago

3 men can construct a wall in 4 days then how many men are required to complete the work in 2 days.

Answers

Answered by vishalns1994
0

Answer:

6 men are required to complete the work in 2 days

Step-by-step explanation:

Given : men M₁ = 3

           Days D₁ = 4

           Days D₂ = 2

          Men M₂ = ?

Solution : Since work is same, then M₁ x D₁ = M₂ x D₂

                                                                  M₂ = M₁D₁/D₂

                                                                       = 3 x 4/2

                                                                       = 12/2

                                                                       = 6 men