3 men can do a piece of work in 12 days. 5 women in 8 days and 20 children in 3 days. In how many days can a man. A woman and a child working together complete the piece of work ?
Answers
Answered by
8
Here Is Your Answer
3 MEN ——— 12 DAYS
1 MEN ———-36 DAYS
5 WOMEN ———- 8 DAYS
1 WOMEN ———- 40 DAYS
20 CHILDREN ———- 3 DAYS
1 CHILDREN ———- 60 DAYS
1 MAN 36
1 WOMAN 40
1 CHILDREN 60
LCM ( 36 , 40 , 60 ) = 360
1 MAN DOES 10 UNITS OF WORK DIALY
1 WOMAN DOES 9 UNITS OF WORK DIALY
1 CHILDREN DOES 6 UNITS OF WORK DIALY
TOTAL = 25 UNITS
360 / 25 =14 (2/5 ) DAYS.
Hope its help you
Answered by
1
Here Is Your Answer
3 MEN ——— 12 DAYS
1 MEN ———-36 DAYS
5 WOMEN ———- 8 DAYS
1 WOMEN ———- 40 DAYS
20 CHILDREN ———- 3 DAYS
1 CHILDREN ———- 60 DAYS
1 MAN 36
1 WOMAN 40
1 CHILDREN 60
LCM ( 36 , 40 , 60 ) = 360
1 MAN DOES 10 UNITS OF WORK DIALY
1 WOMAN DOES 9 UNITS OF WORK DIALY
1 CHILDREN DOES 6 UNITS OF WORK DIALY
TOTAL = 25 UNITS
360 / 25 =14 (2/5 ) DAYS.
Hope its help you