3 men complete a work in 6 days. in 3 days how many men complet this work?
Answers
Answered by
4
3×6=3×m
m=6 days........
m=6 days........
Answered by
1
2 men complete this work
Answered by
3
3men---->6days
xmen---->3days
if you are going to half the amount of time it takes for the work to be completed
then you need twice as many people to complete it in the desired amount of time
hence you will need 6 men
xmen---->3days
if you are going to half the amount of time it takes for the work to be completed
then you need twice as many people to complete it in the desired amount of time
hence you will need 6 men