Math, asked by wither5538, 28 days ago

3 men or 7 women can do a piece of work in 32 days. In how many days will the work be finished if it is done by 6 men and 2 women?​

Answers

Answered by richapariya121pe22ey
1

Step-by-step explanation:

3 men can do a piece of work in 32 days

Therefore, 1 man can do a piece of work in 32×3 days.

7 women can do a piece of work in 32 days.

Therefore, 1 woman can do a piece of work in 32×7 days.