3 person ca paint a house in 8 days. How many persons will be needed if the house is to be painted in 3 days​

Answers

Answered by sukashyap705
1

hope you understand the solution

thanks!!!

Attachments:
Answered by Kaulinx
1

Answer:

0 days cause the house has already been built

Step-by-step explanation:

3per.-8 days

wpersons-3 days

cross multiply

w8=9

collect like terms

w=9/8

w= approximate 1 day