Math, asked by nasheebdangi5172, 5 months ago

3 persons can do a work in 8 days, then 4 persons can do the same work in I) 5 days ii) 6 days iii) 7 days iv) 8 days

Answers

Answered by shalinimaheshwari440
0

Answer:

Third option is correct i.e. 7days

Similar questions