3. To complete a work, A takes 50% more time than B. If together they take
18 days to complete the work, how much time shall B take to do it?
(a) 30 days (6) 35 days (c) 40 days (d) 45 days
Answers
Answered by
1
Answer: Refer attachment below
Step-by-step explanation: