Math, asked by 918279622921, 4 days ago

3. Two men can do a piece of work in 3 days and 6 days respectively. If they work together, in how days will they finish the work ? can do the same niece of work in 2 hours -​

Answers

Answered by jatinsinsinwar260320
0

Answer:

2 days

Step-by-step explanation:

Work done by first man in 3 days = 1

Work done by that man in 1 day= 1/3.

Work done by second man in 6 days = 1

Work done by second man in 1 day= 1/6

Work done by them together in 1 day = 1/3+1/6

= 3/6 = 1/2

So,1/2 work done by them together in 1 day

So, whole work done by them together in days = 2 days

Hence it will take 2 days if they do work together.

Answered by ʍɨֆֆƈʊȶɨɛ
0

Answer:

Given: Three men can complete a piece of work in 6 days. so D2 = 2 days... the correct answer is 2 days.

Similar questions