Math, asked by swathigokulguru, 1 month ago

3. X can do of a work in 10 days.
Y can do 40% of the work in 40
1
days and Z can do of the work
3
in 13 days. Who will complete
the work first?​

Answers

Answered by BANGTAN7BOYS
3

Answer:

here you go

Step-by-step explanation:

✓ X- can do the complete work in =10x4= 40- days.

✓Y- can do the complete work in =40/0.4= 100- days.

✓ X- can do the complete work in =13/(1/3) = 39- days.

Therefore X- can complete the work FIRST.