Math, asked by poojachauhan16, 9 months ago

.
30 men are employed to construct a building in 72 days. Due to some reason, they have
to construct the building in 60 days. How many more men should be employed to
complete the building in 60 days?​

Answers

Answered by tummalaxmisai007
0

Answer:

If the number of workers increases then the time required to complete the task decreases

So if 30 men complete the work in 72 days then to complete the work in 60 days, number of workers needed??

Let the number of workers required be x

30/x=60/72 (inversely proportional)

x=30*72/60=36

In order to complete the work in 60 days 36 workers are required

Hope you are satisfied with the answer

PLEASE MARK AS BRAINLIEST

Similar questions