.
30 men are employed to construct a building in 72 days. Due to some reason, they have
to construct the building in 60 days. How many more men should be employed to
complete the building in 60 days?
Answers
Answered by
0
Answer:
If the number of workers increases then the time required to complete the task decreases
So if 30 men complete the work in 72 days then to complete the work in 60 days, number of workers needed??
Let the number of workers required be x
30/x=60/72 (inversely proportional)
x=30*72/60=36
In order to complete the work in 60 days 36 workers are required
Hope you are satisfied with the answer
PLEASE MARK AS BRAINLIEST
Similar questions
English,
4 months ago
Computer Science,
4 months ago
Hindi,
4 months ago
Social Sciences,
10 months ago
Physics,
1 year ago
Social Sciences,
1 year ago